[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137371":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137371,797,2,"多选题","（2019年真题）国际机电项目实施中的自身风险包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","技术风险",true,{"key":16,"text":17,"correct":14},"B","管理风险",{"key":19,"text":20,"correct":21},"C","财经风险",false,{"key":23,"text":24,"correct":21},"D","法律风险",{"key":26,"text":27,"correct":14},"E","营运风险","ABE","项目实施中自身风险防范措施：（1）建设风险防范（2）营运风险防范（3）技术风险防范（4） 管理风险防范",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]