[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137369":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137369,797,2,"多选题","（2015年真题）采取浇注法进行绝热层施工的要求有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","每次配料必须在规定时间内用完",true,{"key":16,"text":17,"correct":18},"B","应提前制作试块（同时）",false,{"key":20,"text":21,"correct":14},"C","浇注时宜一次浇注成型",{"key":23,"text":24,"correct":14},"D","大面积浇注时，应设对称多浇口",{"key":26,"text":27,"correct":14},"E","间断浇注时，施工缝宜留在伸缩缝的位置上","ACDE","（1）浇注法所采用的模具在安装过程中，应设置临时固定设施。模板应平整、拼缝严密、尺寸 准确、支点稳定，并应在模具内涂刷脱模剂。浇注发泡型材料时，可在模具内带铺衬一层聚乙烯薄膜。（2） 每次配料必须在规定时间内用完。试块的制作，应在浇注绝热层时，同时进行。（3）大面积浇注时，应 设对称多浇日，分段分片进行，并以倒料均匀、封口迅速等操作来控制浇注质量。（4）浇注时应一次浇 注成型，当间断浇注时，施工缝宜留在伸缩缝的位置上。【彩蛋】压轴卷，考前会在金考典考试软件更新哦~ 软件下载链接www.jinkaodian.com（5）浇注不得有发泡不良、脱落、发酥发脆、 发软、开裂、孔径过大等缺陷；当出现缺陷时必须查清原因，重新浇注",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]