[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137366":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137366,797,2,"多选题","（2016年真题）电站锅炉安装质量控制要点包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","安装前确认钢结构高强螺栓连接点安装方法",true,{"key":16,"text":17,"correct":14},"B","锅炉受热面安装前编制专项施工方案并确认符合制造厂要求",{"key":19,"text":20,"correct":14},"C","燃烧器就位再次检查内外部结构",{"key":22,"text":23,"correct":14},"D","对炉膛进行气密试验",{"key":25,"text":26,"correct":27},"E","蒸汽管路冲洗与清洁",false,"ABCD","本题考查的是电站锅炉安装质量控制要点。安装前应确认高强螺拴连接点安装方法，临时螺栓、 定位销数量符合规程要求，安装前编制专项施工方案，确认符合制造要求；燃烧器就位再次检查内外部结 构；锅炉密封工作结束后，对炉膛进行气密试验。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]