[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137362":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137362,797,2,"多选题","（2018年真题）光伏发电工程施工时，汇流箱内的光伏组件串电缆接引前的要求有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","光伏组件侧有明显断开点",true,{"key":16,"text":17,"correct":18},"B","光伏组件侧电缆已连接",false,{"key":20,"text":21,"correct":14},"C","汇流箱内所有开关已断开",{"key":23,"text":24,"correct":14},"D","逆变器侧有明显断开点",{"key":26,"text":27,"correct":18},"E","光伏组件间的插件已连接","ACD","光伏组件之间的接线在组串后应进行光伏组件串的开路电压和短路电流的测试，施工时严禁接触 组串的金属带电部位。 检查汇流箱部件应完好且接线不松动，所有开关和熔断器处于断开状态，汇流箱安装位置符合设计，垂直 度偏差应小于 1.5mm。 逆变器基础型钢其顶部应高出抹平地面 10mm 并有可靠的接地，逆变器安装方向符合设计要求，逆变器本 体的预留孔及电缆管口进行防火封堵。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]