[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137353":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137353,797,2,"多选题","（2014年真题）高压管道安装前，所用管子、管件及阀门等应具有的质量证明文件包括（ ）",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","材料证明",true,{"key":16,"text":17,"correct":14},"B","配件合格证",{"key":19,"text":20,"correct":14},"C","焊接试样试验结果",{"key":22,"text":23,"correct":14},"D","焊接登记表",{"key":25,"text":26,"correct":27},"E","安装试验报告",false,"ABCD","本题考查的是工业管道安装技术要求。所用的管道元件具有合格证等证明文件。所有的管子、管 件、阀门及紧固件等，必须附有材料证明、焊接登记表、焊接试样试验结果、焊缝透视结果、配件合格证及其他验收合格证等证明文件。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]