[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137333":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137333,797,2,"多选题","（2018年真题）关于建筑智能化系统调试检测的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建筑智能化系统调试工作应由项目专业技术负责人主持",true,{"key":16,"text":17,"correct":18},"B","系统检测程序应是分部工程→子分部工程→分项工程",false,{"key":20,"text":21,"correct":18},"C","系统试运行工作应在智能化系统检测完成后进行",{"key":23,"text":24,"correct":18},"D","系统检测汇总记录应由监理工程师填写并做出检测结论",{"key":26,"text":27,"correct":14},"E","系统检测方案经项目监理工程师批准后可以实施","AE","系统检测实施 1.依据工程技术文件和规范规定的检测项目、检测数量及检测方法编制系统检测方案，检测方案经建设单 位或项目监理批准后实施； 2.按系统检测方案所列检测项目进行检测，系统检测的主控项目和一般项目应符合规范规定； 3.系统检测程序：分项工程→子分部工程→分部工程； 4.系统检测合格后，填写分项工程检测记录、子分部工程检测记录和分部工程检测汇总记录； 5.分项工程检测记录、子分部工程检测记录和分部工程检测汇总记录由检测小组填写，检测负责人做出检 测结论，监理（建设）单位的监理工程师（项目专业技术负责人）签字确认。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]