[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137327":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137327,797,2,"多选题","（2015年真题）净化空气系统调试和试运行应具备的条件有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","洁净室建筑装饰验收合格",true,{"key":16,"text":17,"correct":14},"B","各种线管吹扫及试压完成",{"key":19,"text":20,"correct":14},"C","空调设备系统联动完成",{"key":22,"text":23,"correct":24},"D","高效过滤器安装完成",false,{"key":26,"text":27,"correct":14},"E","风量、风压平衡完成","ABCE","净化空调系统的调试和试运转，应在洁净室（区）建筑装饰装修验收合格和各种管线吹扫及试压 等工序完成，空调设备单机试车正常，系统联动完成，风量、压差平衡完毕之后进行。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]