[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137299":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137299,797,2,"多选题","以下属于工业安装工程分部工程质量验收评定中，需要填写的主要内容的是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","分项工程名称",true,{"key":16,"text":17,"correct":14},"B","检验项目数",{"key":19,"text":20,"correct":14},"C","施工单位检查评定结论",{"key":22,"text":23,"correct":14},"D","建设（监理）单位验收结论",{"key":25,"text":26,"correct":27},"E","分部工程验收记录",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]