[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137285":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137285,797,2,"多选题","机电工程施工进度计划调整的内容包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合同工期",false,{"key":16,"text":17,"correct":18},"B","施工内容",true,{"key":20,"text":21,"correct":18},"C","起止时间",{"key":23,"text":24,"correct":18},"D","工作关系",{"key":26,"text":27,"correct":18},"E","资源供应","BCDE","施工进度计划调整的内容：施工内容、工程量、起止时间、持续时间、工作关系、资源供应等。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]