[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137284":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137284,797,2,"多选题","当BCWP＞ACWP＞BCWS时，下列说法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程费用超支，施工进度延误",false,{"key":16,"text":17,"correct":18},"B","工程费用节支，施工进度提前",true,{"key":20,"text":21,"correct":14},"C","应更换效率高的管理人员和施工人员",{"key":23,"text":24,"correct":14},"D","工程费用投入和施工进度维持现状",{"key":26,"text":27,"correct":18},"E","应减少施工作业人员，放慢施工进度","BE","",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]