[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137283":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137283,797,2,"多选题","机电工程施工进度安排中的制约因素有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","工程实体现状",true,{"key":16,"text":17,"correct":14},"B","设备材料进场时机",{"key":19,"text":20,"correct":14},"C","安装工艺规律",{"key":22,"text":23,"correct":14},"D","施工作业人员配备",{"key":25,"text":26,"correct":27},"E","施工监理方法",false,"ABCD","进度计划的安排受工程实体现状、机电安装工艺规律、设备材料进场时机、施工机具和作业人员配备等因素的制约。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]