[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137275":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137275,797,2,"多选题","除专用合同条款另有约定外，合同履行过程中需要进行变更的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","减少合同中的工作",true,{"key":16,"text":17,"correct":18},"B","取消转由他人实施的工作",false,{"key":20,"text":21,"correct":14},"C","追加额外的工作",{"key":23,"text":24,"correct":14},"D","改变合同中的工作质量标准",{"key":26,"text":27,"correct":14},"E","改变工程的位置和尺寸","ACDE","除专用合同条款另有约定外，合同履行过程中发生以下情形的，应进行变更： （1）增加或减少合同中任何工作，或追加额外的工作； （2）取消合同中任何工作，但转由他人实施的工作除外； （3）改变合同中任何工作的质量标准或其他特性； （4）改变工程的基线、标高、位置和尺寸。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]