[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137268":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137268,797,2,"多选题","下列关于炉窑砌筑说法错误的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","动态炉窑砌筑起始点应从热端向冷端或者从低端向高端",false,{"key":16,"text":17,"correct":14},"B","静态炉窑砌筑起始点一般选择自下而上的顺序",{"key":19,"text":20,"correct":14},"C","动态炉窑砌筑必须在炉窑单机无负荷运转验收合格后方可进行",{"key":22,"text":23,"correct":24},"D","静态炉窑砌筑起拱部位应从中间向两侧砌筑",true,{"key":26,"text":27,"correct":24},"E","动态砌筑基本顺序中，预留膨胀缝的紧前工作是分段砌筑","DE","静态炉窑砌筑起拱部位应从两侧向中间砌筑 分段进行修砖及锁砖→膨胀缝的预留及填充",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]