[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137262":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137262,797,2,"多选题","关于节流件安装规定中，不正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","必须在管道吹洗后安装",false,{"key":16,"text":17,"correct":18},"B","必须使流体从节流件的下游端面流向上游端面",true,{"key":20,"text":21,"correct":18},"C","在测量液体时排泄孔的位置在管道的正下方",{"key":23,"text":24,"correct":14},"D","节流件断面应垂直于管道轴线",{"key":26,"text":27,"correct":14},"E","节流件与管件或夹持件同轴","BC","节流件安装应符合下列规定：必须在管道吹洗后安装；必须使流体从节流件上游端面流向下游端面；排泄孔的位置：测量液体时设置在管道正上方；测量气体或蒸汽时设置在管道正下方；断面应垂直于管道轴线（偏差1°）；应与管件或夹持件同轴。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]