[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137259":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137259,797,2,"多选题","下列关于发电机转子穿装前应进行的试验说法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","进行气密性试验",true,{"key":16,"text":17,"correct":18},"B","进行磁道通路试验",false,{"key":20,"text":21,"correct":14},"C","进行漏气量试验",{"key":23,"text":24,"correct":14},"D","试验压力符合制造厂规定",{"key":26,"text":27,"correct":18},"E","允许漏气量符合业主要求","ACD","发电机转子穿装前进行单独气密性试验，重点检査集电环下导电螺钉、中心孔堵板的密封状况，消 除泄漏后应再经漏气量试验，试验压力和允许漏气量应符合制造厂规定。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]