[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137255":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137255,797,2,"多选题","风力发电设备塔筒安装技术中说法错误的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","塔筒分多段供货，现场根据塔筒重量、尺寸以及安装高度选择吊车的吊装工况",false,{"key":16,"text":17,"correct":14},"B","第一节安装前在第一节塔筒下法兰外缘和内缘各涂一圈密封胶以避免湿气进入塔筒内部",{"key":19,"text":20,"correct":21},"C","分别使用力矩扳手、电动扳手和2次液压扳手按要求的拧紧力矩分四次拧紧塔筒螺栓",true,{"key":23,"text":24,"correct":14},"D","用塞尺检测塔筒法兰的间隙",{"key":26,"text":27,"correct":21},"E","使用经纬仪控制塔筒的水平度","CE","塔筒螺栓分别使用电动扳手和2次液压扳手按相应的拧紧力矩分三次进行紧固。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]