[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137248":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137248,797,2,"多选题","钢制储罐建造完毕进行充水试验检查的项目有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","罐底严密性",true,{"key":16,"text":17,"correct":14},"B","罐壁强度及严密性",{"key":19,"text":20,"correct":14},"C","固定顶稳定性",{"key":22,"text":23,"correct":14},"D","浮顶升降试验",{"key":25,"text":26,"correct":27},"E","罐壁的局部凹凸变形",false,"ABCD","①罐底严密性试验 ②罐壁强度及严密性试验 ③固定顶强度及严密性试验 ④固定顶的稳定性试验 ⑤浮顶、内浮顶罐升降试验",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]