[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137244":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137244,797,2,"多选题","工业管道系统压力试验前，应具备的条件是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","管道上的膨胀节己设置临时约束装置",true,{"key":16,"text":17,"correct":14},"B","试验方案已经过批准",{"key":19,"text":20,"correct":21},"C","试验压力表不少于1块",false,{"key":23,"text":24,"correct":21},"D","管道上的安全阀处于自然状态",{"key":26,"text":27,"correct":14},"E","待试管道与无关系统已用盲板隔开","ABE","管道系统试验前应具备的条件： （1）试验范围内的管道安装质量合格。 （2）试验方案已经过批准。 （3）膨胀节已设置了临时约束装置。 （4）试验用压力表合格：精度≥1.6级，表满值应为被测最大压力的1.5?2倍，≥两块，在周期内已校验合格。 （5）管道已加固。待试管道与无关系统已用盲板或其他隔离措施隔开。 待试管道上的安全阀、爆破片及仪表元件等已拆下或加以隔离。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]