[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137225":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137225,797,2,"多选题","设备安装偏差方向的控制要求包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","有利于抵消设备附属件安装后重量的影响",true,{"key":16,"text":17,"correct":14},"B","有利于抵消设备运转时产生的作用力的影响",{"key":19,"text":20,"correct":21},"C","有利于抵消设备运转时产生的振动的影响",false,{"key":23,"text":24,"correct":14},"D","有利于抵消零部件磨损的影响",{"key":26,"text":27,"correct":14},"E","有利于抵消摩擦面间油膜的影响","ABDE","①有利于抵消设备附属件安装后重量的影响； ②有利于抵消设备运转时产生的作用力的影响； ③有利于抵消零部件磨损的影响； ④有利于抵消摩擦面间油膜的影响。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]