[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137149":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137149,797,2,"多选题","机电工程施工总平面布置的原则包括（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","总体布局合理",true,{"key":16,"text":17,"correct":14},"B","降低临时设施的建造费用",{"key":19,"text":20,"correct":14},"C","合理组织交通运输，使施工的各个阶段都能做到交通便捷、运输畅通",{"key":22,"text":23,"correct":14},"D","施工区域的划分保持施工均衡、连续、有序，应既符合施工流程，又使各专业和各工种之间互不干扰",{"key":25,"text":26,"correct":27},"E","尽量增多临时建设设施",false,"ABCD","2020版教材P291 \u002F 2019版教材P276 施工总平面布置的原则1.总体布局合理，施工场地占用面积少，符合节能、环保、安全、消防和文明施工等相关规定。2.合理组织运输，减少二次搬运。3.施工区域的划分和场地的临时占用应符合总体施工部署和施工流程的要求，减少相互干扰。4.充分利用既有建（构）筑物和既有设施为项目施工服务，降低临时设施的建费用。5.临时设施应方便生产和生活，办公区、生活区和生产区宜分离设置。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]