[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137128":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137128,797,2,"多选题","分项工程质量验收记录表签字人为（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工单位专业技术质量负责人",true,{"key":16,"text":17,"correct":18},"B","质监",false,{"key":20,"text":21,"correct":14},"C","建设单位专业技术负责人",{"key":23,"text":24,"correct":18},"D","主管",{"key":26,"text":27,"correct":14},"E","监理工程师","ACE","2020版教材P475\u002F2019版教材P463 5.分项工程质量验收记录应由施工单位质量检验员填写，验收结论由建设（监理）单位填写。填写的主要内容：检验项目；施工单位检验结果；建设（监理）单位验收结论。结论为“合格”或“不合格”。记录表签字人为施工单位专业技术质量负责人；建设单位专业技术负责人；监理工程师。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]