[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137125":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137125,797,2,"多选题","单位工程质量验收合格的规定为（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","单位工程所含分部工程质量全部合格",true,{"key":16,"text":17,"correct":14},"B","子单位工程所含分部工程质量全部合格",{"key":19,"text":20,"correct":21},"C","生产线带负荷试运转全部符合设计要求",false,{"key":23,"text":24,"correct":14},"D","单位工程质量控制资料齐全",{"key":26,"text":27,"correct":14},"E","子单位工程质量控制资料齐全","ABDE","2020版教材P475\u002F2019版教材P463 单位（子单位）工程质量验收合格应符合的规定：单位（子单位）工程所含分部工程的质量应全部为合格。单位（子单位）工程的质量控制资料应齐全",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]