[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137118":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137118,797,2,"多选题","单位工程控制资料检查记录填写的主要内容包括（）等。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","图纸会审、设计变更和协商记录",true,{"key":16,"text":17,"correct":14},"B","材料合格证及检验试验报告",{"key":19,"text":20,"correct":14},"C","隐蔽工程记录、试运转记录",{"key":22,"text":23,"correct":14},"D","质量事故处理记录",{"key":25,"text":26,"correct":27},"E","安全事故隐患处理记录",false,"ABCD","2020版教材P476\u002F2019版教材P464 2.填写的主要内容：图纸会审、设计变更、协商记录、材料合格证及检验试验报告、施工记录、施工试验记录、观测记录、检测报告、隐蔽工程验收记录、试运转记录、质量事故处理记录、中间交接记录、竣工图、分部、分项工程质量验收记录",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]