[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137114":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137114,797,2,"多选题","分部（子分部）工程质量验收记录表签字人包括（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","建设单位项目负责人",true,{"key":16,"text":17,"correct":14},"B","建设单位项目技术负责人",{"key":19,"text":20,"correct":21},"C","监理工程师",false,{"key":23,"text":24,"correct":14},"D","施工单位项目负责人",{"key":26,"text":27,"correct":14},"E","施工单位项目技术负责人","ABDE","2020版教材P475\u002F2019版教材P463 其中工业和建筑工程的记录表签字人均一致。本题考核的是分部（子分部）工程质量验收记录。记录表签字人：建设单位项目负责人；建设单位项目技术负责人；总监理工程师；施工单位项目负责人；施工单位项目技术负责人；设计单位项目负责人。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]