[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137112":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137112,797,2,"多选题","建筑安装工程检验批质量验收的主控项目检验内容中要用数据说明的包括（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","结构的强度",true,{"key":16,"text":17,"correct":14},"B","结构的刚度",{"key":19,"text":20,"correct":21},"C","表面清洁度",false,{"key":23,"text":24,"correct":14},"D","结构的稳定性",{"key":26,"text":27,"correct":14},"E","管道的压力试验","ABDE","2020版教材P480\u002F2019版教材P468 2.主控项目结构的强度、刚度和稳定性等检验数据、工程性能检测。如管道的压力试验；风管系统的测定；电梯的安全保护及试运行等。检查测试记录，其数据及项目要符合设计要求和施工验收规范规定",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]