[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137081":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137081,797,2,"多选题","临时用电通常根据用电设备总容量的不同，应编制（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","临时用电施工组织设计",true,{"key":16,"text":17,"correct":14},"B","安全用电技术措施",{"key":19,"text":20,"correct":14},"C","电气防火措施",{"key":22,"text":23,"correct":24},"D","设备使用计划",false,{"key":26,"text":27,"correct":24},"E","电气平面图、立面图和接线系统图","ABC","2020版教材P451 \u002F 2019版教材P439 （二）临时用电施工组织设计的编制1.临时用电通常根据用电设备总容量的不同，应编制安全用电技术措施和电气防火措施，或临时用电施工组织设计。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]