[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137048":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137048,797,2,"多选题","在竣工验收阶段,收集整理竣工验收资料的重点包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","工程竣工扫尾的资料",true,{"key":16,"text":17,"correct":14},"B","试生产试运行后工程“消缺”",{"key":19,"text":20,"correct":14},"C","尚未完成的工程竣工图",{"key":22,"text":23,"correct":14},"D","试生产试运行情况",{"key":25,"text":26,"correct":27},"E","工程施工总结",false,"ABCD","2020版教材P434 \u002F 2019版教材P423 3. 收集整理竣工验收资料：。资料收集整理的重点是：工程施工扫 尾的资料、试生产试运行后工程“消缺”即整改消除工程缺陷的资料、尚未完成的工程竣 工图和竣工结算的待审稿，以及试生产试运行情况的资料。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]