[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137046":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1137046,797,2,"多选题","建设工程项目必须与主体工程同步验收的项目是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","通风空调工程",false,{"key":16,"text":17,"correct":14},"B","电气工程",{"key":19,"text":20,"correct":14},"C","电梯工程",{"key":22,"text":23,"correct":24},"D","消防工程",true,"2020版教材P432~433 \u002F 2019版教材P421 一、竣工验收的条件 4.环境保护、消防、劳动安全卫生，符合与主体工程“三同时”建设原则，达到国家和地方规定的要求；且工程质量、环境保护、消防、安全、职业卫生、劳动保护、节能、档案等已通过专项验收、核查、评定，可同时交付使用。 2. 专项验收 1）建设工程项目的消防设施、安全设施及环境保护设施应与主体工程同时设计、同时施工、同时投入生产和使用。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]