[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137044":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137044,797,2,"多选题","机电工程联动试运行工序交接中,“三查”包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","查设计漏项",true,{"key":16,"text":17,"correct":14},"B","查未完工程",{"key":19,"text":20,"correct":21},"C","查施工资料",false,{"key":23,"text":24,"correct":14},"D","查工程质量隐患",{"key":26,"text":27,"correct":21},"E","查工程安全隐患","ABD","2020版教材P419 \u002F 2019版教材P408 （1）中间交接已完成：1） “三查四定” 三查：查设计漏项、未完工程、工程质量隐患；四定：对查出的问题定任务、定人员、定时间、定措施）的问题整改消缺完毕，遗留的尾项已处理完。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]