[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137038":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137038,797,2,"多选题","下列竣工结算编制的依据，正确的说法有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","协议书（不包括补充协议）",false,{"key":16,"text":17,"correct":14},"B","投标书（只包括报价工程量清单）",{"key":19,"text":20,"correct":21},"C","相关规范标准",true,{"key":23,"text":24,"correct":21},"D","设计文件",{"key":26,"text":27,"correct":14},"E","进度计划","CD","2020版教材P357 \u002F 2019版教材P343 一、竣工结算编制的依据：1.协议书（包括补充协议）；2.已确认的工程量，结算合同价款及追加或扣减的合同价款；3.投标书及其附件（包含已标价工程量清单）；4.专用、通用合同条款；5.招标工程量清单，相关规范标准、设计文件及有关资料。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]