[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137037":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137037,797,2,"多选题","分部分项工程清单综合单价综合了（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","人工费",true,{"key":16,"text":17,"correct":18},"B","措施费",false,{"key":20,"text":21,"correct":14},"C","材料费",{"key":23,"text":24,"correct":14},"D","利润",{"key":26,"text":27,"correct":18},"E","税金","ACD","2020版教材P252 \u002F 2019版教材P337 清单综合单价中综合了分项工程人工费、材料费、机械费、管理费、利润、人材机价差以及一定范围的风险费用，但并未包括措施费、规费和税金，因此它是一种不完全单价。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]