[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137036":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137036,797,2,"多选题","机电工程施工阶段项目成本控制要点包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制成本计划",false,{"key":16,"text":17,"correct":18},"B","对分解的计划成本进行落实",true,{"key":20,"text":21,"correct":18},"C","核算实际成本",{"key":23,"text":24,"correct":18},"D","进行成本差异分析",{"key":26,"text":27,"correct":14},"E","进行成本分析考评，落实奖惩制度","BCD","2020版教材P347 \u002F 2019版教材P333 施工阶段项目成本控制要点：1、对分解的计划成本进行落实；2.计算实际成本；3、进行成本差异分析；4、注意工程变更",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]