[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137034":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137034,797,2,"多选题","机电工程施工成本控制措施中,属于人工费成本的控制措施有（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","严格劳动组织",true,{"key":16,"text":17,"correct":14},"B","严密劳动定额管理",{"key":19,"text":20,"correct":14},"C","加强技术培训",{"key":22,"text":23,"correct":24},"D","加强施工设备管理",false,{"key":26,"text":27,"correct":24},"E","减少管理人员","ABC","2020版教材P347 \u002F 2019版教材P333 四、施工成本控制措施：1.人工费成本的控制措施。严格劳动组织，合理安排生产工人进出厂时间；严密劳动定额管理，实行计件工资制；加强技术培训，强化生产工人技术素质，提高劳动生产率。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]