[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137030":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137030,797,2,"多选题","机电工程施工进度计划安排中的协调制约因素有（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","工程实体现状",true,{"key":16,"text":17,"correct":14},"B","设备材料进场时机",{"key":19,"text":20,"correct":14},"C","机电安装工艺规律",{"key":22,"text":23,"correct":14},"D","施工机具和人员配备",{"key":25,"text":26,"correct":27},"E","施工组织设计",false,"ABCD","2020版教材P315 \u002F 2019版教材P301 机电工程施工进度计划安排受工程实体现状、机电安装工艺规律、设备材料进场时机、施工机具和作业人员配备等诸因素的制约，协调管理的作用是把制约作用转化成和谐有序相互创造的施工条件，使进度计划安排衔接合理、紧凑可行，符合总进度计划要求。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]