[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137021":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137021,797,2,"多选题","施工待优化中,进行经济合理性比较包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","各方案的一次性投资总额",true,{"key":16,"text":17,"correct":18},"B","各方案实施的可靠性",false,{"key":20,"text":21,"correct":18},"C","各方案资源节约、污染降低程度",{"key":23,"text":24,"correct":14},"D","各方案的资金时间价值",{"key":26,"text":27,"correct":14},"E","各方案对环境影响的损失","ADE","2020版教材P290~291 \u002F 2019版教材P276 （2）经济合理性比较 1）比较备方案的一次性投资总额; 2）比较各方案的资金时间价值; 3）比较各方案对环境影响的损失; 4）比较各方案总产值中剔除劳动力与资金对产值增长的贡献; 5）比较各方案对工程进度时间及其费用影响的大小; 6）比较各方案综合性价比。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]