[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137018":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137018,797,2,"多选题","施工组织设计的修改或补充涉及原则的重大变更，须履行原审批手续，原则的重大变更指（）等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程设计无重大修改",false,{"key":16,"text":17,"correct":18},"B","有关法律、法规、规范和标准实施、修订和废止",true,{"key":20,"text":21,"correct":18},"C","主要施工方法有重大调整",{"key":23,"text":24,"correct":18},"D","主要施工资源配置有重大调整",{"key":26,"text":27,"correct":18},"E","施工环境有重大改变","BCDE","2020版教材P293 \u002F 2019版教材P278 1.施工组织设计一经批准，施工单位和工程相关单位应认真贯彻执行，未经审批不得修改。施工组织设计的修改或补充涉及原则的重大变更，须履行原审批手续。原则的重大变更包括：工程设计有重大修改；有关法律、法规、规范和标准实施、修订和废止；主要施工方法有重大调整；主要施工资源配置有重大调整；施工环境有重大改变等。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]