[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137013":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137013,797,2,"多选题","停工待检 （H）点应包括（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","重要工序节点",true,{"key":16,"text":17,"correct":14},"B","隐蔽工程",{"key":19,"text":20,"correct":21},"C","重要部位的加工",false,{"key":23,"text":24,"correct":14},"D","关键的试验验收点",{"key":26,"text":27,"correct":14},"E","不可重复试验验收点","ABDE","2020版教材P279 \u002F 2019版教材P265 停工待检点的监督2.重要工序节点、隐蔽工程、关键的试验验收点或不可重复试验验收点。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]