[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1137010":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1137010,797,2,"多选题","机电工程施工索赔的起因包括（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","不可抗力因素",true,{"key":16,"text":17,"correct":14},"B","工程环境变化",{"key":19,"text":20,"correct":14},"C","合同变更",{"key":22,"text":23,"correct":24},"D","合同条文齐全",false,{"key":26,"text":27,"correct":14},"E","合同对方违约，不履行或未能正确履行合同义务与责任","ABCE","2020版教材P267 \u002F 2019版教材P253 1.索赔的起因（1）合同当事方违约，不履行或未能正确履行合同义务与责任。（2）合同错误，如合同条文不全、错误、矛盾等，设计图纸、技术规范错误等。（3）合同变更；工程环境变化，包括法律、物价和自然条件的变化等。（4）不可抗力因素，如恶劣气候条件、地震、洪水、战争状态等。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]