[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136989":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136989,797,2,"多选题","耐火浇注料施工程序中，在材料验收和施工面清理后，浇注前还应做好（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","膨胀缝预留",false,{"key":16,"text":17,"correct":18},"B","锚固钉焊接",true,{"key":20,"text":21,"correct":18},"C","模板制作安装",{"key":23,"text":24,"correct":18},"D","防水剂涂刷",{"key":26,"text":27,"correct":18},"E","浇注料搅拌和试块制作","BCDE","2020版教材P165 \u002F 2019版教材P153 （一）耐火挠注料的施工程序：材料检查验收→施工面清理→锚固钉焊接→模板制作安装→防水剂涂刷→浇注料搅拌井制作试块→挠注并振捣→拆除模板→膨胀缝预留填充→成品养护。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]