[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136965":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136965,797,2,"多选题","设备及管道系统的防潮层常用的施工方法有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","金属保护法",false,{"key":16,"text":17,"correct":18},"B","捆扎法",true,{"key":20,"text":21,"correct":14},"C","充填法",{"key":23,"text":24,"correct":18},"D","涂抹法",{"key":26,"text":27,"correct":14},"E","浇注法","BD","2020版教材P154 \u002F 2019版教材P144 防潮层施工常采用涂抹法和捆扎法。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]