[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136947":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136947,797,2,"多选题","自动化线路敷设完毕后，应进行的工作有（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","校线",true,{"key":16,"text":17,"correct":14},"B","标号",{"key":19,"text":20,"correct":14},"C","埋设的线路应设置明显标识",{"key":22,"text":23,"correct":14},"D","测量电缆电线的绝缘电阻",{"key":25,"text":26,"correct":27},"E","在线路的起端处加标志牌",false,"ABCD","2020版教材P131 \u002F 2019版教材P121 (8)线路敷设完毕,应进行校线和标号,并要求测量电缆电线的绝缘电阻，在线路终端处,应加标志牌。地下埋设的线路，应设置明显标识。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]