[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136943":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136943,797,2,"多选题","自动化仪表工程的验收分为（）步骤进行。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分项工程验收",true,{"key":16,"text":17,"correct":18},"B","隐蔽工程验收",false,{"key":20,"text":21,"correct":14},"C","分部工程验收",{"key":23,"text":24,"correct":18},"D","检验批",{"key":26,"text":27,"correct":14},"E","单位工程竣工验收","ACE","2020版教材P131 \u002F 2019版教材P121 自动化仪表工程验收分为分项工程验收、分部工程验收和单位工程竣工验收三个步骤。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]