[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136940":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136940,797,2,"多选题","测量蒸汽压力的压力取源部件应安装在管道的（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","管道的上半部",true,{"key":16,"text":17,"correct":14},"B","下半部与管道水平中心线成0~45°夹角范围内",{"key":19,"text":20,"correct":21},"C","管道的下半部",false,{"key":23,"text":24,"correct":21},"D","下半部与管道水平中心线成45~90°夹角范围内",{"key":26,"text":27,"correct":21},"E","下半部与管道水平中心线成45~60°夹角范围内","AB","2020版教材P137 \u002F 2019版教材P126 测量蒸汽压力时，应在管道的上半部，以及下半部与管道水平中心线成0~45°夹角范围内。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]