[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136934":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136934,797,2,"多选题","自动化仪表工程的温度取源部件在管道上开孔及焊接，必须在管道（）前进行。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","制作",false,{"key":16,"text":17,"correct":18},"B","防腐",true,{"key":20,"text":21,"correct":18},"C","衬里",{"key":23,"text":24,"correct":18},"D","压力试验",{"key":26,"text":27,"correct":14},"E","安装","BCD","2020版教材P136 \u002F 2019版教材P125 （3）在设备或管道上安装取源部件的开孔和焊接，必须在设备或管道的防腐、衬里和压力试验前进行。在高压、合金钢、有色金属设备和管道上开孔时，应采用机械加工的方法。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]