[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136929":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136929,797,2,"多选题","自动化仪表安装的施工准备阶段工作是保证工程顺利进行的重要环节，其主要工作内容包括（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","参加施工图设计文件会审",true,{"key":16,"text":17,"correct":14},"B","编制施工预算",{"key":19,"text":20,"correct":21},"C","各控制室布置",false,{"key":23,"text":24,"correct":14},"D","工机具和标准仪器的准备",{"key":26,"text":27,"correct":21},"E","编制施工进度计划","ABD","2020版教材P130 \u002F 2019版教材P120 （1）参加施工图设计文件会审，编制施工预算 （2）技术准备。编制自动化仪表工程安装施工组织设计或自动化仪表工程施工方案已批准。 （3）进行技术交底。明确所承担施工任务的特点、技术质量要求、系统的划分、施工工艺、施工要点和注意事项，强调工程技术的具体要求、安全措施、施工程序等。 （4）施工机具、标准仪器、仪表设备及材料的准备。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]