[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136917":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136917,797,2,"多选题","发电机转子穿装前应单独进行（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","气密性试验",true,{"key":16,"text":17,"correct":18},"B","磁道通路试验",false,{"key":20,"text":21,"correct":14},"C","漏气量试验",{"key":23,"text":24,"correct":14},"D","试验压力符合制造厂规定",{"key":26,"text":27,"correct":18},"E","允许漏气量符合业主要求","ACD","2020版教材P127 \u002F 2019版教材P117 发电机转子穿装前进行单独气密性试验，消除泄漏后应再经漏气量试验，试验压力和允许漏气量应符合制造厂规定。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]