[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136912":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136912,797,2,"多选题","锅炉受热面组件吊装的一般原则包括（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","先下后上",false,{"key":16,"text":17,"correct":14},"B","先中间后两侧",{"key":19,"text":20,"correct":21},"C","先上后下",true,{"key":23,"text":24,"correct":21},"D","先两侧后中间",{"key":26,"text":27,"correct":14},"E","上下同时安装","CD","2020版教材P121 \u002F 2019版教材P111 锅炉钢架施工验收合格后，即可进行锅炉受热面组件的吊装。锅炉受热面组件吊装的一般原则是:先上后下，先两侧后中间。先中心再逐渐向炉前、炉后、炉左、炉右进行。同一层杆件的吊装顺序为立柱、垂直支撑（斜撑）、横梁、小梁、水平支撑、平台、爬梯、栏杆等。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]