[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136899":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136899,797,2,"多选题","多层和高层钢结构的多节柱安装时，每节钢柱的定位轴线的下列导引方法中，不正确的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","从地面控制轴线直接引上",false,{"key":16,"text":17,"correct":18},"B","从中层柱的轴线引上",true,{"key":20,"text":21,"correct":18},"C","从顶端控制轴线直接引下",{"key":23,"text":24,"correct":18},"D","从上层柱的轴线引下",{"key":26,"text":27,"correct":18},"E","从下层柱的轴线引上","BCDE","2020版教材P119 \u002F 2019版教材P109 多节柱安装时，每节柱的定位轴线应从地面控制轴线直接引上，不得从下层柱的轴线引上，避免造成过大的积累误差。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]