[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136891":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136891,797,2,"多选题","关于管道安装现场条件的表述，正确的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","管道组成件及管道支承件等已检验合格",true,{"key":16,"text":17,"correct":18},"B","管道施工前，安装单位应当向管道安装工程所在地负责管道使用登记的质量技术监督部门书面告知",false,{"key":20,"text":21,"correct":14},"C","临时供水、供电、供气等设施已满足安装施工要求",{"key":23,"text":24,"correct":14},"D","与管道连接的设备安装已找正合格、固定完毕，标高、中心线、管口方位符合设计要求",{"key":26,"text":27,"correct":18},"E","施工单位已编制施工组织设计并报建设单位进行审核","ACD","2020版教材P91 \u002F 2019版教材P81 （二）现场条件1.与管道有关的土建工程经检查合格，满足安装要求并办理了交接手续。临时供水、供电、供气等设施已满足安装施工要求。2.与管道连接的设备己找正合格、固定完毕，标高、中心线、管口方位符合设计要求。3.管道组成件及管道支承件等已检验合格。4.管子、管件、阀门等内部己清理干净，无杂物，其质量应符合设计文件的规定。5.在管道安装前完成有关工序。例如:脱脂、内部防腐与衬里等已进行完毕。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]