[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136883":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136883,797,2,"多选题","在工业管道安装前应完成工作有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","清洗",false,{"key":16,"text":17,"correct":18},"B","脱脂",true,{"key":20,"text":21,"correct":18},"C","内防腐",{"key":23,"text":24,"correct":18},"D","衬里",{"key":26,"text":27,"correct":14},"E","试压","BCD","2020版教材P92 \u002F 2019版教材P81 5.在管道安装前完成有关工序。例如：脱脂、内部防腐与衬里等已进行完毕。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]